On-Site Generation & Air

Natural-gas generation, backup systems, emissions, and air quality.

Representative photograph of backup generators and electrical infrastructure at a data center in Mesa, Arizona. Not Project Mustang. Photo: Rsparks3 / Wikimedia Commons (CC0 1.0).

The October development agreement confirms that a power-generation facility remains part of Taylor Technology Campus, while the detailed 84–112-unit / 125-foot-stack configuration comes from the withdrawn August Employment Center proposal and should be retained as historical, not final, design evidence.

Last verified October 9, 2026

What the Current Project Records Show

October 2026 development agreement

October agreement keeps on-site generation in project scope

The agreement defines the Project to include a power-generation facility and associated electrical transmission/distribution infrastructure. The agreement provisions reviewed here do not establish the August unit count or a final primary-generation MW limit.

Current agreement
August 2026 historical proposal / disclosure

84–112 gas engines / stacks

The submitted plan lists 84 to 112 gas-unit engines/stacks, with a stated per-unit capacity of 12.5 MW.

Proposed / documented
August 2026 historical proposal / disclosure

Approximately 1.05–1.40 GW nameplate

Multiplying the stated unit count by 12.5 MW yields approximately 1,050 to 1,400 MW of aggregate gas-generator nameplate capacity if all listed units are installed. This is a calculated range, not a confirmed operating output.

Calculated
August 2026 historical proposal / disclosure

Separate diesel backup generation

The plan lists 3-MW diesel-fired backup generators and two life-safety backup generators per data-center building. Planning materials also depict emergency/life-safety backup generation.

Proposed / documented
August 2026 historical proposal / disclosure

Hearing figure: approximately 1,040 MW

Project representatives described roughly 1,040 MW of on-site generation at the August 18 hearing. The separate Employment Center equipment schedule lists 84–112 units at 12.5 MW each, which implies a broader 1.05–1.40 GW theoretical nameplate range if every listed unit were installed. The discrepancy remains an important item to reconcile as engineering advances.

Hearing + submitted schedule
August 2026 historical proposal / disclosure

Stacks up to approximately 125 feet

Planning disclosures allow gas-generation stacks up to approximately 125 feet. Exact stack coordinates, diameters, exhaust temperatures and final source locations have not been published.

Proposed / documented
August 2026 historical proposal / disclosure

Black-start and diesel systems

The current concept includes diesel backup generation for data-center buildings and separate black-start diesel generation in addition to the natural-gas generation system.

Proposed / documented
Tier 4 distinction: The October agreement’s air-quality clause requires EPA Tier 4 compliance for diesel backup generators and other non-road equipment. That language does not state that the primary natural-gas generation plant itself is subject to the same Tier 4 non-road-engine standard. Air permitting for the primary generation remains a separate TCEQ/federal issue.

Air-Quality Review

The October agreement places air-quality compliance under applicable federal/state law and contains a specific Tier 4 requirement for diesel backup generators and other non-road equipment. The August planning record remains evidence of the larger gas-generation concept. Neither source, by itself, establishes final engine models, final emissions rates, final stack parameters, or a completed Project-specific air permit.

What Is Still Unknown

  • Final engine manufacturer, model, quantity and operating schedule.
  • Final annual and hourly emissions for the complete campus.
  • Final stack count, stack parameters and dispersion-modeling results.
  • Project-specific TCEQ authorizations applicable to the final generation configuration.
  • How often on-site gas generation would operate relative to grid service.
Official recordCalculatedStill unresolved

Primary sources: October 2026 development agreement and Additional Regulations; August 2026 Employment Center Plan and Planning & Zoning hearing disclosures. August equipment counts remain historical proposal evidence until superseded by final engineering or permitting. Documents & sources →