Noise

Cooling equipment, transformers, generation, testing, setbacks, and enforcement.

Representative photograph of industrial cooling equipment. Not Project Mustang. Photo: Victor Moragriega / Pexels.

The October development agreement now contains the current negotiated Project-specific noise and setback framework for Taylor Technology Campus, superseding the withdrawn August Employment Center proposal as the current City agreement text.

Last verified October 9, 2026

What the Current Project Records Show

October 2026 development agreement

65 dBA or pre-development baseline

Before permits are issued, an acoustic study must establish existing baseline dBA levels along the property boundaries. Except for allowed construction periods, project noise at a property line adjacent to property developed with and/or zoned for single-family residential use may not exceed the greater of 65 dBA or the measured pre-development level.

Current agreement
October 2026 development agreement

300-foot residential-adjacency building setback

No building may be located within 300 feet of directly adjoining property that is zoned residential or developed with an existing residential use under the agreement’s stated conditions.

Current agreement
October 2026 development agreement

700-foot south setback for data center, gas plant and BESS

The data center, gas plant and BESS may not be located closer than 700 feet from the southern property line; accessory buildings must be at least 500 feet from that line.

Current agreement
October 2026 development agreement

Electrical screening / undergrounding near residential boundaries

Except for the Oncor switchyard and specified surface facilities, private electrical utilities within 300 feet of qualifying residential boundaries are generally required underground, and private substations within that distance require an eight-foot masonry screen.

Current agreement

What the Standard Does Not Yet Resolve

The required baseline study has not yet established the actual pre-development values that could control the allowable level. The agreement does not create a separate nighttime dBA limit, an express dBC/low-frequency limit, a detailed tonal/impulsive-noise penalty, or a published continuing-monitoring schedule in the provisions reviewed here.

The agreement improves on the earlier August wording by including certain existing residential uses as well as residential zoning, but the protection still turns on specific property-line and adjacency language. Actual residence-to-equipment distances will depend on final site design.

What We Are Still Tracking

  • Baseline nighttime acoustic measurements.
  • dBA and dBC / low-frequency measurement requirements.
  • Octave-band or one-third-octave analysis and tonal treatment.
  • Final setbacks for generation, substations, transformers and major mechanical equipment.
  • Commissioning, complaint-triggered testing and ongoing monitoring.
Official proposalBaseline / final controls unresolved

Primary source: October 2026 Taylor Technology Campus development agreement and Additional Regulations. August Employment Center noise/setback language is retained only as historical comparison. Documents & sources →